  • #31
    Re: Starting 42" NW Pensylvania

    It has not stopped raining here for weeks, 18.75" have fallen since May 1 . As you can see from my photograph I have not made much progress due to the rain, only two more chains completed.

    I was warned by Boylanta a builder/forum member not to use FB board due to his constant worries of getting it wet during his build. I can not stress enough what a bad decision it was for me to use FB board.

    Am I worrying to much? I need someone to weigh in how concerned I need to be about it getting damp/wet, am I going to have structural problems? I keep it tarped but even so it seems to be very moist when I uncover it due to curing concrete/small leaks of rain.

    Help
    Chris

    Link to my photo album:
    https://www.flickr.com/photos/hodgey...7646087819291/

    Link to my build: http://www.fornobravo.com/forum/f21/...nia-19366.html

    Comment


    • #32
      Re: Starting 42" NW Pensylvania

      your FB board shouldn't be a problem if you have kept your oven tarped. I am more curious about your hearth, which appears to be slab on grade. Did you add anything to waterproof the concrete? If not, wicking is likely to be an issue. Could be that you are getting moisture coming up through the slab if you have had that much rain.

      I built my oven the same way (slab on grade), but added xypex to the hearth concrete mix to prevent wicking. If you didn't do something like this, you'll have problems. You'll need to dig some pretty substantial french drains around the oven to carry away moisture.

      edit: read back to the start of your thread. My $.02 is that plastic vapor barrier is probably not sufficient by itself to prevent wicking. Water is going to find its way in through the edges, through condensate. If your board is covered and still feeling wet, I suspect that's the issue. I had my oven under tarp through a very wet Seattle spring, and never had an significant moisture problems with the FB Board.
      Last edited by deejayoh; 07-08-2013, 10:30 AM.
      My build progress
      My WFO Journal on Facebook
      My dome spreadsheet calculator

      Comment


      • #33
        Re: Starting 42" NW Pensylvania

        After the encouragement from the forum members I have stepped back away from the ledge and realized that the FB board is not going to collapse from being moist "as I was fearing" after one of the wettest June/Julys ever here. Where I live receives more annual rain fall then Seattle 36.2", us 42.7" and we had nearly 19" in the short period of May/June/July .

        The last weekend thou hot and muggy, made for good working conditions "no rain" and good progress on my WFO. As you can see from the pictures, I was able to complete rings 8, 9, 10 and 11. Also, "which I enjoyed thoroughly" I removed the inner arch form. The prospective from there is awesome to see for the first time. What a enjoyable sight.

        I am now down to the last two or three rings to be completely enclosed. After finishing ring 11, I am finding it extremely difficult to build with the indefensible tool only. I'm contemplating removing IND tool trying the exercise ball technique? If anyone could way in with any advice it would be greatly appreciated.
        Chris

        Link to my photo album:
        https://www.flickr.com/photos/hodgey...7646087819291/

        Link to my build: http://www.fornobravo.com/forum/f21/...nia-19366.html

        Comment


        • #34
          Re: Starting 42" NW Pensylvania

          Hod,

          You can use notched sticks, plywood disc, fish hook or modify you IT too
          Russell
          Google Photo Album [https://photos.google.com/share/AF1Q...JneXVXc3hVNHd3/]

          Comment


          • #35
            Re: Starting 42" NW Pensylvania

            Hodgey,
            I used a combination of the IT w/ some strips of 1/2" plywood.
            I rounded the ends of the plywood w/ a belt sander, which made it easier to adjust the length by wedging the sticks where needed.
            See the pics below.

            Once the IT got the brick in place, I wedged a plywood stick in place & moved the IT for the next brick.

            Todd B.

            Originally posted by UtahBeehiver View Post
            Hod,

            You can use notched sticks, plywood disc, fish hook or modify you IT too
            Todd

            Link to my build - http://www.fornobravo.com/forum/f21/...ast-18900.html

            Comment


            • #36
              Re: Starting 42" NW Pensylvania

              Looks like you are still using 1/2 bricks. It will be easier if you move to using thirds. Not as much weight to slide off.

              Personally, with the smaller bricks I found that if the mortar was mixed right and I held the brick for a few seconds, I could get the bricks to stay in place with no additional support. But all the suggestions above are good ones if that is not working for you.
              My build progress
              My WFO Journal on Facebook
              My dome spreadsheet calculator

              Comment


              • #37
                Re: Starting 42" NW Pensylvania

                Todd, Russell and Deejay, all great ideas that I'll try to use and thank you all for your input. The last ring I completed "11" I used quarter bricks.
                Chris

                Link to my photo album:
                https://www.flickr.com/photos/hodgey...7646087819291/

                Link to my build: http://www.fornobravo.com/forum/f21/...nia-19366.html

                Comment


                • #38
                  Re: Starting 42" NW Pensylvania

                  Here is a look at ring 11.
                  Chris

                  Link to my photo album:
                  https://www.flickr.com/photos/hodgey...7646087819291/

                  Link to my build: http://www.fornobravo.com/forum/f21/...nia-19366.html

                  Comment


                  • #39
                    Re: Starting 42" NW Pensylvania

                    One trick that really helps when you get this far is if you lay one brick for the next ring when you finish so that you have something for the others to grab onto.
                    My build progress
                    My WFO Journal on Facebook
                    My dome spreadsheet calculator

                    Comment


                    • #40
                      Re: Starting 42" NW Pensylvania

                      A look at ring 12
                      Chris

                      Link to my photo album:
                      https://www.flickr.com/photos/hodgey...7646087819291/

                      Link to my build: http://www.fornobravo.com/forum/f21/...nia-19366.html

                      Comment


                      • #41
                        Re: Starting 42" NW Pensylvania

                        It is my 12th week since starting this major backyard project. I have just completed the 13th ring and only have the Keystone at the very top of the dome left to have it fully enclosed. I have posted pictures below.

                        The last two rings I have begun cutting each brick using the bevel/angle method "wish I had from start". Thanks to MrChipster's posts and all the information from Boylanta. Once again I am going to repeat what a invaluable source the forum is and its members who's are so willing to help. There's no question in my mind that I would have never thought about starting this project without Forno Bravo and its members on the forum.

                        I hope to complete the outer chimney this weekend so I can start the curing process. My initial plan/dreams where to be able to cook pizzas for my birthday next week but that's not looking possible unless I could become unemployed and that wouldn't make my wife very happy!
                        Chris

                        Link to my photo album:
                        https://www.flickr.com/photos/hodgey...7646087819291/

                        Link to my build: http://www.fornobravo.com/forum/f21/...nia-19366.html

                        Comment


                        • #42
                          Re: Starting 42" NW Pensylvania

                          Hurry and plug it before it leaks!!!!!

                          Comment


                          • #43
                            Re: Starting 42" NW Pensylvania

                            Looks great to me .Are you still having problems with the insulation and slab?


                            Bill

                            Comment


                            • #44
                              Re: Starting 42" NW Pensylvania

                              Originally posted by hodgey1 View Post
                              It is my 12th week since starting this major backyard project. I have just completed the 13th ring and only have the Keystone at the very top of the dome left to have it fully enclosed. I have posted pictures below.

                              The last two rings I have begun cutting each brick using the bevel/angle method "wish I had from start". Thanks to MrChipster's posts and all the information from Boylanta. Once again I am going to repeat what a invaluable source the forum is and its members who's are so willing to help. There's no question in my mind that I would have never thought about starting this project without Forno Bravo and its members on the forum.

                              I hope to complete the outer chimney this weekend so I can start the curing process. My initial plan/dreams where to be able to cook pizzas for my birthday next week but that's not looking possible unless I could become unemployed and that wouldn't make my wife very happy!
                              I am glad I could provide some assistance but I was helped by others and all of my brick cutting jig development came from the insight that people like JCG31 provided before me. I hope you will be able to pay forward to others on the forum in the future on the things you learn.
                              Chip

                              Comment


                              • #45
                                Re: Starting 42" NW Pensylvania

                                Bill, Thankfully the rains here have subsided for the most part enabling me to make some pretty good progress. The FB board seems to be holding up well even thou subjected to quit a bit of moisture earlier during construction.

                                This weekend I completed the 14th ring, the dome is now fully enclosed. I also did some clean up in the interior and finished the outer arch. Pics below.

                                Chipster, thanks again and I'm doing my best to pay it forward with my posts as I continue with the project.

                                Chris
                                Last edited by hodgey1; 08-05-2013, 06:44 AM. Reason: Spelling
                                Chris

                                Link to my photo album:
                                https://www.flickr.com/photos/hodgey...7646087819291/

                                Link to my build: http://www.fornobravo.com/forum/f21/...nia-19366.html

                                Comment