Just discovered that I put the other 3 threads in the wrong forum. If you want to see the first 3 with pics, go to the Pomoeii oven construction forum.
The weather is very much against me at the present, constant rain and more rain. For those not in the know, South Australia is very much in the need of rain as we are on water restrictions.
This however did not stop me as I set up a small tarp over the oven and carried on regardless. Mixing the poor man?s mortar was an experience. 3 parts sand, 1 hydrated lime, 1 fireclay and 1 portland cement, was sticky and quite difficult to mix in the wheel barrow. I couldn?t be bothered using the mixer as I was only mixing enough to put in the base layer of soldier bricks and the bricks holding the steel arch oven frame. Three rows later, I had used it all up. Great to work with as it is exceptionally sticky and really grabs onto the bricks, very handy when working on chains 3 and over with very sloping bricks.
I cut and installed the hearth this afternoon and redid the arch and another chain of the oven tonight. Will post these pics next time as I only finished 2 hours ago in the dark, in fact did them with the aid of the flood light and a double fluoro.
Neill
The weather is very much against me at the present, constant rain and more rain. For those not in the know, South Australia is very much in the need of rain as we are on water restrictions.
This however did not stop me as I set up a small tarp over the oven and carried on regardless. Mixing the poor man?s mortar was an experience. 3 parts sand, 1 hydrated lime, 1 fireclay and 1 portland cement, was sticky and quite difficult to mix in the wheel barrow. I couldn?t be bothered using the mixer as I was only mixing enough to put in the base layer of soldier bricks and the bricks holding the steel arch oven frame. Three rows later, I had used it all up. Great to work with as it is exceptionally sticky and really grabs onto the bricks, very handy when working on chains 3 and over with very sloping bricks.
I cut and installed the hearth this afternoon and redid the arch and another chain of the oven tonight. Will post these pics next time as I only finished 2 hours ago in the dark, in fact did them with the aid of the flood light and a double fluoro.
Neill
Comment