Hello. My name is Fabio in it's been a wile since I have gotten on hte forum, due to work related injuries. I am in the final stages of actually constructing the oven. Work stopped some time ago but very soon finish the actual construction of the oven. I have some questions for anyone that can help me with some technical info.
I am building a 42" Tuscan oven, which is under a roof of a outdoor kitchen. The kitchen /patio is shaped in the form of "L" with the oven closing the upper portion of the "L" @ an angle. I have a 12' rounded end bartop with 18'x16' of counter top space, sink, fridge, and wood burning BBQ pit. Electrical run with lights etc. I will be posting some pictures soon , from biginning to what has been done so far. I live in SoCal and the hearth is completed but when the top slab of the hearth was poured I did not insulate it as someone had suggested. So now these are some of the questions that I have.
I have a 10" tile saw that I purchased for some tile work, and was wondering if it is worth cutting each brick to fit tight against each other, or just do it th e way most people have done itwith mortar in between bricks. If it is better to cut the bricks, does anyone have the correct angle of the cuts. I do not remember who posted some drawings that appeared to have been done with a cad program and showed each layer and how it was constructed, but that is what I want to do.
1. Can I still pour let say an 1, 1-1/2" on top of the hearth before laying the main firebricks base first, or is it necessary.
2. In some past pictures I have noticed some one had the main soldier bricks standing straight up and some were cut in half. Which is correct.
3. Once the layers of the walls have been constructed, and sealed do I need to insulate in between the oven and outer section with foil or fire blanket for added insulation or can I just pour about an 1" 0r 1-1/2" of fireclay mortar on top of the oven for mass.
4. What is the correct mixture of fireclay, sand, and cement. I'll be using shovel for measuring or should I be dead on with mixture.
5. Does anyone know where I can purchase a thermometer for this oven, since it will get hot, and a regular thermometer will not work!
6. I will be using sheet metal double insulated flute from Home Depot any suggestions. Is it OK to use this type, since i am going through the roof. By the way the flute will have an slight "S" type bent, not so quite as sharp with the bends, will this hamper the amount of exaust.
7. Do I need a thermal slab before I lay the main bricks. I will be using the yellow firebricks, which I had the supplier call the manufacture to get the right amount of temperature these bricks can handle. They said 1,800 degrees, and the red bricks can handle 2,300 degrees.
Thank you in advance for any help with this info, I am sure I am forgetting something but if I do I'll ask againg.
Ciao Fabio.
P.S. Some of the info I had checked out was from dmun, paulages,and ColonelCorn76.
I am building a 42" Tuscan oven, which is under a roof of a outdoor kitchen. The kitchen /patio is shaped in the form of "L" with the oven closing the upper portion of the "L" @ an angle. I have a 12' rounded end bartop with 18'x16' of counter top space, sink, fridge, and wood burning BBQ pit. Electrical run with lights etc. I will be posting some pictures soon , from biginning to what has been done so far. I live in SoCal and the hearth is completed but when the top slab of the hearth was poured I did not insulate it as someone had suggested. So now these are some of the questions that I have.
I have a 10" tile saw that I purchased for some tile work, and was wondering if it is worth cutting each brick to fit tight against each other, or just do it th e way most people have done itwith mortar in between bricks. If it is better to cut the bricks, does anyone have the correct angle of the cuts. I do not remember who posted some drawings that appeared to have been done with a cad program and showed each layer and how it was constructed, but that is what I want to do.
1. Can I still pour let say an 1, 1-1/2" on top of the hearth before laying the main firebricks base first, or is it necessary.
2. In some past pictures I have noticed some one had the main soldier bricks standing straight up and some were cut in half. Which is correct.
3. Once the layers of the walls have been constructed, and sealed do I need to insulate in between the oven and outer section with foil or fire blanket for added insulation or can I just pour about an 1" 0r 1-1/2" of fireclay mortar on top of the oven for mass.
4. What is the correct mixture of fireclay, sand, and cement. I'll be using shovel for measuring or should I be dead on with mixture.
5. Does anyone know where I can purchase a thermometer for this oven, since it will get hot, and a regular thermometer will not work!
6. I will be using sheet metal double insulated flute from Home Depot any suggestions. Is it OK to use this type, since i am going through the roof. By the way the flute will have an slight "S" type bent, not so quite as sharp with the bends, will this hamper the amount of exaust.
7. Do I need a thermal slab before I lay the main bricks. I will be using the yellow firebricks, which I had the supplier call the manufacture to get the right amount of temperature these bricks can handle. They said 1,800 degrees, and the red bricks can handle 2,300 degrees.
Thank you in advance for any help with this info, I am sure I am forgetting something but if I do I'll ask againg.
Ciao Fabio.
P.S. Some of the info I had checked out was from dmun, paulages,and ColonelCorn76.