Announcement

Collapse
No announcement yet.

Pouring the hearth

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • Pouring the hearth

    If one plans on having a hearth made up of a concrete slab and an insulated slab on top of it do you wait until the concrete dries/cures before poring the insulated slab and, if so, how long do you wait before pouring?
    Also, is the surface of the insulated slab diferent in appearance and texture from the conrete slab? That is, will it have the same finished look?
    Lastly, if you want to add color to the slab will the two different types of concrete end up looking the same?

    Thanks
    bobnnorm@ptd.net

  • #2
    Re: Pouring the hearth

    Hey I am new to this and will build this summer; but I am in construction and if you leave the hearth slab a little rough then when you pour the insulating slab it will have "tooth" to attach to the lower one and then finish the insulated slab with a hard trowel finish ( flat). As for color if you add the same amount of color to each slab they should be close to the same color the insulating materials might cause some color variation, that I am not sure about. And you should not have to wait until the lower slab cures before installing the insulation slab on top. There maybe other threads out there that are more correct than what I have said, I am coming from general construction experience.

    Comment


    • #3
      Re: Pouring the hearth

      You do not have to wait between pours. In fact, the original Pompeii oven plans actually directed you to pour the perlite concrete or vermiculite concrete immediately after the support slab. The thinking was to get the best possible bond. It has been proven to not be necessary. NEITHER slab is going anywhere once poured and the oven built. So, if you want to or need to take a break between pours there will be no problems.

      Insulating concrete (perlcrete/vermicrete) will both have a consistancy of oatmeal. YES, it will look funny and be a bit crumbly when dry, this is totally normal. Everyone seems to come on the forum directly after the pour, concerned something is not right. Do not be alarmed and give it a week to dry before proceeding with your floor and dome. A 5-1 ratio of perlite OR vermiculite and portland cement.

      As for color, WHY? the insulating layer CANNOT be left exposed and must have some type of finish applied if extended beyond the footprint of the oven. The area under the oven is just that...under the oven so it won't be seen. The same applies if you are using it for your dome insulation, it must be finished. Even when used in a concrete mix, both perlite and vermiculite can absorb a tremendous amount of water (that is why it is used as a soil additive and conditioner by gardeners and horticulturists). Each grain can absord 10 times its weight in water. Speaking from experience, you do not want to have a saturated insulating layer at anytime after your oven is built.

      RT

      Comment


      • #4
        Re: Pouring the hearth

        RT is correct. I, personally, would do the insulation pour the following day. The form work is going to be different anyway. The insulating layer will be smaller and "inside" the suspended slab.

        Try to limit the insulating layer to between the suspended slab and the the oven. It should only be to the footprint of the brickwork and the corresponding insulating layer over the dome. Do not extend it to the edge of the suspended slab.

        Comment


        • #5
          Re: Pouring the hearth

          finish the insulated slab with a hard trowel finish ( flat).
          I think you will find it is hard to get any kind of finish on the vermiculite concrete. About the best you will be able to do is pat it flatish. That's why a leveling medium is called for, between the insulating slab and the brick floor.
          My geodesic oven project: part 1, part 2

          Comment


          • #6
            Re: Pouring the hearth

            Originally posted by RTflorida View Post
            Do not be alarmed and give it (the vermiculite or perlite mix) a week to dry before proceeding with your floor and dome.
            Hi, is a week really necessary before you can proceed with the next step?

            I think you will find it is hard to get any kind of finish on the vermiculite concrete. About the best you will be able to do is pat it flatish.
            If it is difficult to get the Perlite or Vermiculite concrete flat, surely the oven floor bricks that are laid on top of it will be really uneven?

            Thanks again for your help,

            LEAO +
            www.leon.cat

            Comment


            • #7
              Re: Pouring the hearth

              Hi Bobnnorm,

              Here are my comments, I hope they help.

              You don't actually "pour" vermiculite or perlite concrete. You shovel it in or dump from a bucket. Please don't tamp it down hard, just enough to fill the corners of the form. You don't want to compact it, it is insulation and relies on air voids. Use an angle iron or 2 x 4 to screed the surface of the vermiculite/perlite concrete. It should be level but you cannot smooth it. Place FB insulation board or other board over the concrete insulation if you want a smooth surface OR use a clay/sand mix to level the hearth bricks. I used 1/2" ceramic insulation board under my last oven to provide a smooth surface for the hearth bricks.

              The concrete slab doesn't need a trowel finish except where it will be visible. It is advisable to use an "edging tool" to round the edges of the slab though. Go around once when the concrete is still wet to push the bigger stones down, then again when the concrete begins to set-up a little firmer. No need to get too precise about this since most of it will never be seen. I wish I could remember the forum member that recommended this. Maybe he will read this and offer additional helpful comments.

              The vermicrete insulation should be firm enough after a couple of days. If you make your wooden forms using screws then you can leave them in place while you do the hearth work then unscrew the forms several days later.

              The vermicrete layer stays very wet. It will set up rather slowly compared to a concrete slab and it will be crumbly if you bump it or rub a brick against it.

              Cheers,
              Bob

              Here is the link to my oven number 1 construction photos!

              Here is the link to my oven number 2 construction photos!

              Comment


              • #8
                Re: Pouring the hearth

                Moisture underneath the floor in the perlcrete or vermicrete layer is the most difficult to remove later on, so if you have the time wait a few weeks for it to dry before covering with the floor bricks, which are going to have a tendency to lock the moisture in. I'm assuming fine weather here, you don't want any extra rain on top of it. The amount of water in the vermicrete layer is approx. double that which you would use in a standard concrete mix, so there is a lot to remove, why not let nature do the job for you if you have time.
                Apologies if this advice is contrary to the Pompeii plans, just my advice from experience.
                Kindled with zeal and fired with passion.

                Comment


                • #9
                  Re: Pouring the hearth

                  Originally posted by david s View Post
                  Moisture underneath the floor in the perlcrete or vermicrete layer is the most difficult to remove later on, so if you have the time wait a few weeks for it to dry before covering with the floor bricks, which are going to have a tendency to lock the moisture in. I'm assuming fine weather here, you don't want any extra rain on top of it. The amount of water in the vermicrete layer is approx. double that which you would use in a standard concrete mix, so there is a lot to remove, why not let nature do the job for you if you have time.
                  Apologies if this advice is contrary to the Pompeii plans, just my advice from experience.
                  I would like to add one additional thought to this topic. the Vermiculite - Portland cement mix is a type of concrete ant thus should be cured damp. I highly recommend a plastic tarp or drop cloth to keep it from drying out to rapidly during the first 5 days or so - this will allow it to cure properly.

                  Just my two cents.
                  Chip
                  Chip

                  Comment


                  • #10
                    Re: Pouring the hearth

                    True , but as it's not really structural it's less of an issue. Additionally the extra water in the vermiculite should be sufficient to allow full hydration for that first week as the thing dries slowly, but covering would not hurt.
                    Kindled with zeal and fired with passion.

                    Comment


                    • #11
                      Re: Pouring the hearth

                      I will qualify this question before going any further . I am a total noob just starting my oven but from what I think I understand in reading this thread is that the vermicrete slab goes on top of a concrete slab , so from the bottom up it would be ....concrete , vermicrete fire brick . In reading the book "the bread builders " , I understand the pictures to be vermicrete , concrete , and fire brick , again from the bottom up . Which order is correct? Thanks for the clarification.
                      My Oven Build
                      http://www.fornobravo.com/forum/f6/s...ult-18532.html

                      Comment


                      • #12
                        Re: Pouring the hearth

                        Jim, Here it is from the top down

                        Outside above the oven - Sky and clouds and sometimes rain and snow
                        Roof or igloo shell - Weather protection
                        Insulation - Ceramic blanket, loose fill of perlite or vermiculite or vermicrete
                        Dome fire bricks
                        Hot oven - inside the oven where you cook and burn wood
                        Floor Fire Brick - optional soapstone
                        Ceramic board insulation (optional - but highly recommended)
                        Vermicrete - a less expensive but less effective insulating layer than ceramic board
                        Structural Concrete with rebar or rewire.
                        Outside below the oven and or the stand or structure that the whole thing sits on.
                        Ground - Mother earth

                        Attached is a drawing of just the area you asked about

                        Chip
                        Attached Files
                        Last edited by mrchipster; 10-10-2012, 09:26 AM.
                        Chip

                        Comment


                        • #13
                          Re: Pouring the hearth

                          Chip , thanks for the drawing . This is opposite what alan scott teaches , correct? What is th advantage to doing it this way ? Does the weight of the completed , cladded oven tend to compress the vermicrete? Thanks so much for the explanations.
                          My Oven Build
                          http://www.fornobravo.com/forum/f6/s...ult-18532.html

                          Comment


                          • #14
                            Re: Pouring the hearth

                            Alan Scott was a great breadmaker, but a horrible oven designer.

                            Comment


                            • #15
                              Re: Pouring the hearth

                              Originally posted by jim81147 View Post
                              Chip , thanks for the drawing . This is opposite what alan scott teaches , correct? What is th advantage to doing it this way ? Does the weight of the completed , cladded oven tend to compress the vermicrete? Thanks so much for the explanations.
                              Jim,

                              Insulate the hot areas to the benefit of higher oven temps, lower wood usage, and longer retained heat for additional cooking the next or longer days into the future, my oven is built this way and i am often cooking 5 days after i put out the fire.

                              The only possible reason I can think of for concrete below the bricks, before the insulation; is additional floor mass and that can easily be achieved by standing the firebrick on their sides and only if you are a serious bread baker and i mean 50 loaves a day each and every day, I can turn out 20 loaves of bread before needing to reheat my oven and that is the day after having a fire in the oven. I only have a single layer of bricks and they are laid out thin side not on edge.

                              The fun of the oven for me is producing all of the various forms of food that can be made by the differing temperatures you get as the temp goes down,

                              Pizza on fire night, Steak or seafood the next day over hot coals, bread that afternoon or evening or the following day, Roasts stews or other baked goods the 3rd day, slow cooked foods and or ribs on days 4 and 5 and dehydrating and drying like jerkey on days 5 6 and 7 then back to fire. or if I choose; Fire it back up mid week for something special.

                              It is all easy and good if well insulated. besides it fires up real quick with minimal wood if the oven is already hot. or part way to hot.

                              The vermicrete is very strong in compression so no worries about it compacting once firm and cured.

                              And thanks to this post and FB for my new Rank as "Master Builder"

                              Chip
                              Last edited by mrchipster; 10-10-2012, 07:36 PM.
                              Chip

                              Comment

                              Working...
                              X