I visited a Forno Bravo dealer today, was impressed with the product, and am ready to forge ahead with the project. However, the foundation remains a significant obstacle. Since I am new to most construction (I built a chicken coop- that's it) I don't really even know what to tell a contractor about the job.
I have selected a site, obtained a permit, and hired a concrete contractor, explained my requirements, however, it appears that he spread a large variety of gravel over the existing area without digging it out, and didn't use a compactor.
I have since read that digging below the frost line is important in installing a concrete slab.
Do I start from scratch- remove the gravel, dig down 24 inches (I live in Pennsylvania) and then re-gravel and compact the gravel? Is it important to use pea gravel as mentioned in the Pompeii oven plans?
Another question is whether the pad can be larger than the oven foundation- I was planning to make mine 9 x 11 so as to have extra room for counter space, but now I'm concerned that the weight differential (under the oven versus under the counter) will make the pad prone to cracking. Should I play it safe and just make the pad the recommended size in the Pompeii plans?
Also, I have read that there are some concrete additives that make the mixture much less prone to cracking in cold weather. Should I look into that?
So many questions.
Thanks for your help.
I have selected a site, obtained a permit, and hired a concrete contractor, explained my requirements, however, it appears that he spread a large variety of gravel over the existing area without digging it out, and didn't use a compactor.
I have since read that digging below the frost line is important in installing a concrete slab.
Do I start from scratch- remove the gravel, dig down 24 inches (I live in Pennsylvania) and then re-gravel and compact the gravel? Is it important to use pea gravel as mentioned in the Pompeii oven plans?
Another question is whether the pad can be larger than the oven foundation- I was planning to make mine 9 x 11 so as to have extra room for counter space, but now I'm concerned that the weight differential (under the oven versus under the counter) will make the pad prone to cracking. Should I play it safe and just make the pad the recommended size in the Pompeii plans?
Also, I have read that there are some concrete additives that make the mixture much less prone to cracking in cold weather. Should I look into that?
So many questions.
Thanks for your help.
Comment