Chimney placement: Convention is for the chimney to be in front and just outside the cooking chamber. Most folks want to be able to close off the cooking chamber and be able to retain maximum heat for baking (without an actual fire or live coals present). That does mean that you will need to make a landing and a reveal (for a firing/cooking door) beyond the cooking chamber/hearth. I know you are talking about just limited firings for primarily pizza...but I hate to see you limit options when the oven could do so much more.
I used the same type of premixed refractory mortar for my oven dome and had the same concerns. Once the bricks are actually set in place in your vault arch, they really don't need a lot of mortar to keep them in place. That's the beauty of arch's design strength. The main issue I had using the pre-mix stuff is that with the thicker applications it does crack and open up as it dries...hence the call for thin layers. There is a homebrew high heat mortar described in the forum that is much cheaper to make and doesn't have the same cracking issues. I initially bought a couple of 5 gallon pails of the pre-mix and ended up needing to buy a lot more. I simply kept filling the big gaps and then the following cracks with more mortar. Eventually I got them all filled, but it was more expensive than making my own mortar would have been. The homebrew heat mortar doesn't have anywhere near the same issues. One note here, if you are cutting the vault bricks with proscribed angles for the arch radius, they fit more tightly together and you obviously use much less mortar. Cutting the brick is more work, but worth it in many ways. Look up the homebrew formula on the forum--it's fastest to google "home brew mix forno bravo" or "homebrew forno bravo" to get a better idea of its advantages...note: make sure to add the forno bravo or you get a lot of beer references...
...not bad, just not on point. Also you might look at the other barrel vault builds documented in the forum for chimney placement.As to collapsing barrel vaults...don't remember any and since your oven doesn't have a huge dome vault as is on the smaller side it probably will not have any major problems with the outer oven facade as support.
Pictures of your build and oven location (and even a scanned sketch of what you're thinking about building) really help us to help you.
Here's just one link to a build on site that shows some of what you'll have to consider during your build...his has a little flatter arch than semi-circle so he has thicker side walls that do the needed buttressing.
https://community.fornobravo.com/for...el-vault-build






!