And hopefully one day gets finished.
Been browsing the forum for a while and thought I'ld show some progress of my build.
I realise its probably not the best way to go, but like with most things I build I have a rough plan and then just work out the rest as I go.
So I picked an area for the oven, got approval from the boss, and started digging and pulling up pavers. Discovered a drain pipe running from the back yard out to the front so had to build form over that. Over all wasn't too much work. Put down some road base, borrowed a mates compactor, laid down just a little reo and ordered a minimix truck to bring the concrete. Was a bit worried that It would take a while to unload and have to pay exorbitant waiting time fee, but got 12 barrow loads of in 10 minutes. Missus helped shovel it to where it was needed. For first time doing anything other than setting a pole in concrete was fairly happy with result.
Next came the block laying. Was hoping to just dry stack and core fill. Would have probably worked but blocks weren't very even so had a go at laying with mortar. I think I was just trying to lay them with too little mortar wanting to keep the joints close, which was causing frustration with trying to keep them level. Finally got the first coarse down and wasn't too bad from there.
Chopped up some rebar and went back to the wheelbarow and mixed up about 18 loads to do the core fill. Since the last photo have filled the remaining cores with road base because I have heaps on hand.
Will knock up the form for upper slab in the new year, and was going to just mix that myself but am leaning to getting a truck back again.
cheers
shane
Having a bit of trouble with photos, will keep trying,
Been browsing the forum for a while and thought I'ld show some progress of my build.
I realise its probably not the best way to go, but like with most things I build I have a rough plan and then just work out the rest as I go.
So I picked an area for the oven, got approval from the boss, and started digging and pulling up pavers. Discovered a drain pipe running from the back yard out to the front so had to build form over that. Over all wasn't too much work. Put down some road base, borrowed a mates compactor, laid down just a little reo and ordered a minimix truck to bring the concrete. Was a bit worried that It would take a while to unload and have to pay exorbitant waiting time fee, but got 12 barrow loads of in 10 minutes. Missus helped shovel it to where it was needed. For first time doing anything other than setting a pole in concrete was fairly happy with result.
Next came the block laying. Was hoping to just dry stack and core fill. Would have probably worked but blocks weren't very even so had a go at laying with mortar. I think I was just trying to lay them with too little mortar wanting to keep the joints close, which was causing frustration with trying to keep them level. Finally got the first coarse down and wasn't too bad from there.
Chopped up some rebar and went back to the wheelbarow and mixed up about 18 loads to do the core fill. Since the last photo have filled the remaining cores with road base because I have heaps on hand.
Will knock up the form for upper slab in the new year, and was going to just mix that myself but am leaning to getting a truck back again.
cheers
shane
Having a bit of trouble with photos, will keep trying,
Comment