A while ago I asked for some advice regarding my oven build which I had plans to start.
Well, now I have managed to get this thing started and have just poured my suspended slab to form my hearth.
Before I begin building the oven chamber I was hoping to run a couple more questions by the knowledge of the pro's on here!!
I now plan on poring a vermiculite concrete slab, on which I will have calcium sil board then my firebricks.
How long should I leave the vermiculite concrete before starting the brickwork? (will be covered up)
Do I need to install any kind of fire break between the inner entrance arch, which will be formed out of fire brick, and the outer entrance arch?
I have read that when using fire cement, the joint with should be tight, i.e less than 5mm.
When I build the chains of the dome what is best practice to do with the outside of the dome where the joint width will be larger, (I don't plan on cutting each brick with a taper!)?
Many thanks in advance again.
I will get some photos up of the build when done!
Cheers
Allan
Well, now I have managed to get this thing started and have just poured my suspended slab to form my hearth.
Before I begin building the oven chamber I was hoping to run a couple more questions by the knowledge of the pro's on here!!
I now plan on poring a vermiculite concrete slab, on which I will have calcium sil board then my firebricks.
How long should I leave the vermiculite concrete before starting the brickwork? (will be covered up)
Do I need to install any kind of fire break between the inner entrance arch, which will be formed out of fire brick, and the outer entrance arch?
I have read that when using fire cement, the joint with should be tight, i.e less than 5mm.
When I build the chains of the dome what is best practice to do with the outside of the dome where the joint width will be larger, (I don't plan on cutting each brick with a taper!)?
Many thanks in advance again.
I will get some photos up of the build when done!
Cheers
Allan