On the Forno Bravo instruction page 59 Ver. 1.2 Material list 36" oven it states:
(8) 10' lengths of 1/2" rebar, (4) cut to 80";(4) cut to 94"
(4) 2"x6"x8' studs for framing, (2) cut to 83";(2) cut to 94"
My question is, if the slab is only 71x80", why do I need such longer rebar and stud framing?
Am I missing something? thanks Carlo
(8) 10' lengths of 1/2" rebar, (4) cut to 80";(4) cut to 94"
(4) 2"x6"x8' studs for framing, (2) cut to 83";(2) cut to 94"
My question is, if the slab is only 71x80", why do I need such longer rebar and stud framing?
Am I missing something? thanks Carlo