Can I remove arch form before mortar is dry?
Collapse
X
-
Imo if it were home brew mortar, if there are wedges under the arch form that can be removed to allow it be lowered gently, and there is buttressing on the soldier course, it should be ok to lower the form for cleaning after an hour or so. But, I can't see enough in the pic to be sure about all of that.Joe Watson " A year from now, you will wish that you had started today" My Build Album / My Build
-
I've never used air set refractory mortar. My understanding is that it takes about 48 to 72 hours for it to set. (A much longer time than homebrew which is about an hour imo). And, that it takes high heat to really cure it to the point that water won't dissolve it. Maybe someone else will weigh in here, but I think that I would take that into consideration. It sounds like your soldier courses can't kick out on you so the arch should be fine if you can be careful letting the arch form down. I am sure that you know by now that the concrete behind the soldier courses is going to suck a lot of heat out of your oven.Joe Watson " A year from now, you will wish that you had started today" My Build Album / My Build
Comment
-
Originally posted by Gulf View PostI've never used air set refractory mortar. My understanding is that it takes about 48 to 72 hours for it to set. (A much longer time than homebrew which is about an hour imo). And, that it takes high heat to really cure it to the point that water won't dissolve it. Maybe someone else will weigh in here, but I think that I would take that into consideration. It sounds like your soldier courses can't kick out on you so the arch should be fine if you can be careful letting the arch form down. I am sure that you know by now that the concrete behind the soldier courses is going to suck a lot of heat out of your oven.
Comment
Comment