Announcement

Collapse
No announcement yet.

NZ build

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • david s
    replied
    Click image for larger version

Name:	P6160027.jpg
Views:	253
Size:	86.6 KB
ID:	385835 Click image for larger version

Name:	P6160030.jpg
Views:	235
Size:	131.3 KB
ID:	385834

    So long as there is plenty of draw from the flue provided by a combination of pipe diameter and height, the entry below the pipe can actually be really quite shallow. Think of a vacuum cleaner head that is wider than the pipe but far shallower. So long as the entry funnels nicely to the pipe and the draw is adequate there are no smoke issues. This is quite difficult to achieve if making the thing in brick because it's hard to transition from a rectangle to a circle. Casting allows this far more easily as pics show.
    Last edited by david s; 02-22-2016, 03:29 AM.

    Leave a comment:


  • JSeward
    replied
    Thanks gents, I have sketch-up to hand, but what am I actually trying to achieve ? Sounds like I can make a small entry work ? Is it the building of it that is difficult or is it the fact that a short landing causes venting/draw issues ? I am confused

    Leave a comment:


  • JRPizza
    replied
    JSeward, do you have any experience using CAD programs? Laying bricks and using templates are great tools, but using CAD can help you do some quick resizing and moving things around. Two things that I think will help you shorten up your landing is to go with a smaller flue and move the inner arch as far into the oven as possible. There are recommendations for flue size here on the forum, but for your size oven the recommendation would be for an 8" round if you went with round. If you shrunk your oven to around 36" (.915m) the recommendation is for a 6 round that would let you have a smaller vent area. Moving the inner arch in towards the center of the oven lets you start the vent "earlier" which could shorten up the landing length too. Lastly, you could add a cantilever to the front of your hearth to gain some room - several builders have done that.
    I recommend reading several of the posts on sizing a vent landing and consider using some CAD program or hand layouts to get a quick feel for what is possible.

    Leave a comment:


  • david s
    replied
    Ceramic fibre blanket is twice as good an insulator as vermicrete so you can make your insulation 50mm thick and save some more space. Your bigger problem is the depth of the entry.. Lay some bricks out on your slab to see if you can work it out. Casting an entry is a way of making it much shallower than a brick one. Mine is only 130mm deep and then another 65mm for the decorative arch in front of it. You can also set the entry slightly inside the circumference of the dome to save more space.

    Leave a comment:


  • JSeward
    replied
    Thanks David, base is 1.4m square, building out of brick, bricks available are 75x115x230. What diameter would you recommend for this size of base ?

    I am guessing 100mm of vermicrete on the outside is the norm, so using the above 970mm would seem like it fits. My main worry was the minimum length of the entry required to allow the oven to draw properly, I think this is really what will dictate the diameter of the dome.

    Cheers

    Leave a comment:


  • david s
    replied
    With the measurements you've provided it sounds like a squeeze. You don't say if you are building the oven in brick, casting yourself or using a modular kit, but if it's brick then a half brick will be 112 mm which only leaves you 88 mm each side for insulation and rendered outer shell or siding if building a dog kennel style. If casting or buying a modular kit the walls are usually thinner so that might be a better way to go, or just make the oven smaller. You don't say what the other dimension of your supporting slab is, but most designs need extra room to accomodate the depth of the entry, so this also needs consideration.

    Leave a comment:


  • JSeward
    started a topic NZ build

    NZ build

    Hi All I have finally stopped lurking and decided to join up. What a great bunch you are! I have built my base and about to start the hearth and dome, though not really working to a formal set of plans I am getting nervous about the dome. My base is 1.4m give or take, the inner diameter of the dome was hoping to be 1.0m, do I have enough room for the landing and chimney ? It is looking a little shorter than most pics I have seen. Width of opening I was hoping to be 50cm and about 30cm high. Dome inner height of 50cm. Any help much appreciated
    Last edited by JSeward; 02-20-2016, 05:33 PM.