Hey folks. I'm in the middle of building a base out of red bricks. The walls will be double bricked - the outer layer several courses higher to accommodate the elevated slab. My question is what should the thickness ratio be between the concrete slab and the insulation (vermicrete) layer above?
A course of bricks is 2.5" high. So two extra outer courses will leave a 5" cavity. Would something like 4" for the concrete slab work, with a 1" vermicrete insulation layer? Or should I add an extra course (7.5" cavity) and go 4" concrete slab and 2.5" vermicrete?
Cavity depth is constricted to multiples of brick height as this will make it possible to perfectly level things off afterwards.I'm in the middle of building a base out of red bricks. The walls will be double bricked - the outer layer several courses higher to accommodate the elevated slab. My question is what should the thickness ratio be between the concrete slab and insulation (vermicrete) layer?
A course of bricks is 2.5" high. So two extra outer courses will leave a 5" cavity. Would something like 4" for the concrete slab work, with a 1" vermicrete insulation layer? Or should I add an extra course (7.5" cavity) and go 4" concrete slab and 2.5" vermicrete?
Cavity depth is constricted to multiples of brick height as this will make it possible to perfectly level things off afterwards.
A course of bricks is 2.5" high. So two extra outer courses will leave a 5" cavity. Would something like 4" for the concrete slab work, with a 1" vermicrete insulation layer? Or should I add an extra course (7.5" cavity) and go 4" concrete slab and 2.5" vermicrete?
Cavity depth is constricted to multiples of brick height as this will make it possible to perfectly level things off afterwards.I'm in the middle of building a base out of red bricks. The walls will be double bricked - the outer layer several courses higher to accommodate the elevated slab. My question is what should the thickness ratio be between the concrete slab and insulation (vermicrete) layer?
A course of bricks is 2.5" high. So two extra outer courses will leave a 5" cavity. Would something like 4" for the concrete slab work, with a 1" vermicrete insulation layer? Or should I add an extra course (7.5" cavity) and go 4" concrete slab and 2.5" vermicrete?
Cavity depth is constricted to multiples of brick height as this will make it possible to perfectly level things off afterwards.





Comment