I'm digging my foundation now and am a bit confused. I know to lay in rebar in upper and lower portions of my 12"x16" perimeter footing and to put rebar every 12" both ways for the thinner slab area in the middle. I plan on having steel rebar in every-other block hole (all of this per the official Pompeii plans and others posts).
BUT...do I put vertical re-bar sticking out of the top of my concrete pour for every block hole I plan to fill with concrete? AND...if I do, do I just do my best to screed, level and float between the rebar? Please take a look at my attached pdf drawing and you'll see my question in item #3.
Thanks (in advance) for all your advice.
Dino
BUT...do I put vertical re-bar sticking out of the top of my concrete pour for every block hole I plan to fill with concrete? AND...if I do, do I just do my best to screed, level and float between the rebar? Please take a look at my attached pdf drawing and you'll see my question in item #3.
Thanks (in advance) for all your advice.
Dino
Comment