Hey,
Dome pieces were much tighter together prior to cap being placed. Upon application of cap for dome all pieces had to be moved outward to permit its placement. I now have about 1/4 to 3/8 inch spaces between all modular oven pieces. Will this be a problem ? I also have a 1/4 inch space between the oven floor and walls.
Thanks,
Peter
Dome pieces were much tighter together prior to cap being placed. Upon application of cap for dome all pieces had to be moved outward to permit its placement. I now have about 1/4 to 3/8 inch spaces between all modular oven pieces. Will this be a problem ? I also have a 1/4 inch space between the oven floor and walls.
Thanks,
Peter





. I did the mortar work myself, get 2 inch trowel, a spray bottle, bucket and the mortar. Wet the seams on the dome prior to the application as per diagrams on the disc. Remember to place the eyelets so you can secure the insulation later. The insulation is not heavy but it is nasty stuff so use long sleeves, goggles, gloves(rubber textured from HD or Lowes) and a mask. Guess it took me about 3 hrs. I secured the insulation later(4-5 days) with wire secured through the eyelets. Can't wait to see your photos...I just finished the stucco on the durarock I'll send a picture.
Comment