On my first oven I did the slow cure before I put the insulation on. I have noticed on my updated instructions for the build of the Pompeii that it is recommended to wait one week after the oven is completed.
Does this mean after insulation is on and also stucco?
I was hoping to put on the insulation (3 x one inch inslulating blanket) and then put on the first coat of stucco. This would bring me to 5 days or so after the brick work is complete, then I would start the oven cure for 5 days while the first coat of stucco also cures. Then I could put on the top coat of stucco and a few more days of curing and then pizza time.
Does this sound like a reasonable approach?
Looking at my pictures from my last build I see I cured before insulation was put in place and all was well. No big cracks after about 3 years of use. I am guessing the instructions have changed since the pdf files were first sent out but maybe I just did not read into them properly.
Thanks Wayne
Does this mean after insulation is on and also stucco?
I was hoping to put on the insulation (3 x one inch inslulating blanket) and then put on the first coat of stucco. This would bring me to 5 days or so after the brick work is complete, then I would start the oven cure for 5 days while the first coat of stucco also cures. Then I could put on the top coat of stucco and a few more days of curing and then pizza time.
Does this sound like a reasonable approach?
Looking at my pictures from my last build I see I cured before insulation was put in place and all was well. No big cracks after about 3 years of use. I am guessing the instructions have changed since the pdf files were first sent out but maybe I just did not read into them properly.
Thanks Wayne