Re: Johnfm43 Build
John -
it's looking real good. We've had some strange weather this spring / summer in Northern California - it's tripped me up a bit as well.
X
-
Re: Johnfm43 Build
I got the first few courses of block layed over the last couple of days. I also got the steel cut and welded so, I should be able to finish the block today. I used 2X2 3/8" angle iron. I saw two different numbers in the instructions. So I went with the larger of the two. I have a tendency to go overboard on most of my builds. I have put in a picture of the kids playhouse that the wife and I build in 2008. As you can tell overkill.
I started laying the electrical I am hopeing to have an outlet and two lights on the oven. I am still thinking about the thermocouplers. I have read most of the post on the issue and still not sure if I want to put out the money for them and a reader.
More Pics I hope at the end of the day.
Johnfm43
Leave a comment:
-
Re: Johnfm43 Build
Well as I have reported the other day I have the slab poured and things are starting to go up. Here a few pictures from the pour and the finished slab. As you can tell from the pictures it rained hard the morning of the pour. We had to build a huge tent over the area. We had it colored and stamped.
Thank goodness for one of our friends that had gone to ranger school in the military, he knew how to tie knots and engineer stuff.
We also poured a 6X24 foot fire wood box slab. This should help with keeping the wood dry during the winter.
More to report soon.
Johnfm43
Leave a comment:
-
Johnfm43 Build
As you guys can see my Join Date was 08-09-2008. I have been researching for almost a full 3 years. Time and Money have been the two big problems. I broke ground when school got out. I just have been trying to do as much as I can myself. So here goes with my build.
My plan is to build a WFO, Parrilla, and fireplace. I am not sure how far I can get before I return to work. But, I will do what I can.
So far I have dug out the area 35'X14'. Installed water, drains (I burried two 55 Gallon drums that had the bottoms removed, I filled them with drain rock put the lid back on and covered up) and electricial. I installed 3 inches of road base and 4 inches of concrete, 7 inches in the WFO area, wire mesh and rebar. Then the day of the pour it rained hard. We had to tent the area. I did pay a local guy to finish and stamp the pad. We poured the outdoor kitchen pad and a firewood pad which worked out to be 8 yards. It is time tomorrow to start the block stand.
Here are some early pictures. More to come as I go along.
I do still need to buy fire bricks. I do need 9 dark ones for an idea I have. Has anyone ever used the black ones. Can't say what I am doing with them you will have to follow along to see.
Thanks Johnfm43
Helpers in the one pictures brought me drain rock to fill up the drums.
Attached Thumbnails
I know that this is the same post as in Getting started. But, I did not know how to move thread to the right location.Tags: None
Leave a comment: