I’m on a time limit…
Building a 940mm internal diameter Pompeii and I’ve just started the 6th course. Internal arch built and I have all the materials I need to complete. I now have a time limit for grandsons birthday in a few weeks so I’ve got 6 three day weekends. Is this feasible?
W’end 1: Finish 6th and 7th courses. Start 8th.
W’end 2: Finish 8th, 9th and 10th.
W’end 3: Finish dome and build outer arch.
W’end 4: Wrap with 3 layers insulting blanket and vermicrete the dome (and render?).
W’end 5: First fires to cure.
W’end 6: Take to pizza temps.
W’end 7: Party time…
I’m not sure about the vermicrete and then rendering it (stucco?). Do I need to leave time between these two operations? I don’t mind leaving the final finish for a while if I have to. In fact, if everything goes pear shaped, could I leave the insulation off completely and fire up the oven with no insulation? Just make sure no-one leans against it…
And it seems logical to me to get a few fires going to dry out the dome before I put the insulation and vermicrete on. Then a few more to get the moisture out of that when it’s complete. Any comments?
Building a 940mm internal diameter Pompeii and I’ve just started the 6th course. Internal arch built and I have all the materials I need to complete. I now have a time limit for grandsons birthday in a few weeks so I’ve got 6 three day weekends. Is this feasible?
W’end 1: Finish 6th and 7th courses. Start 8th.
W’end 2: Finish 8th, 9th and 10th.
W’end 3: Finish dome and build outer arch.
W’end 4: Wrap with 3 layers insulting blanket and vermicrete the dome (and render?).
W’end 5: First fires to cure.
W’end 6: Take to pizza temps.
W’end 7: Party time…
I’m not sure about the vermicrete and then rendering it (stucco?). Do I need to leave time between these two operations? I don’t mind leaving the final finish for a while if I have to. In fact, if everything goes pear shaped, could I leave the insulation off completely and fire up the oven with no insulation? Just make sure no-one leans against it…
And it seems logical to me to get a few fires going to dry out the dome before I put the insulation and vermicrete on. Then a few more to get the moisture out of that when it’s complete. Any comments?