    Curing fire

    I have finished the dome, fire brick and refractory mortar. Waiting to insulate until after curing fires. Question: how many days do I wait between setting last brick and starting fire?
  • UtahBeehiver
    Member Moderator
    • May 2012
    • 5260

    #2
    Lee, current thought is to have the dome insulated before cure to min. Temp differential from inside to outside dome. Then final render after cure
    Russell
    https://photos.google.com/album/AF1Q...L9lr_UnUgJbF3Z

    Comment

    • LeeBird
      Serf
      • Sep 2018
      • 13

      #3
      Thanks Russell, that makes perfect sense. Do I need to wait and give the mortar time before lighting the fire?

      Comment

      • UtahBeehiver
        Member Moderator
        • May 2012
        • 5260

        #4
        You could start with a halogen shop light, gets you around 125 - 150 f(now) then charcoal 200 ish (cook something, dutch oven or so), then fires. Back tomorrow will text you abt insul.