I know a lot of us end up making vermicrete, either for isulation under the hearth or for a layer around the fire dome. I've even used it as finish roofing (not my best idea... see thread ...), and as an inner layer on the wooden doors I use on the other ovens to keep them from burning up.
Problem I've had in the past always came in getting an uniform distribution of concrete mixed throughout the vermiculite. General method has always been to get the vermiculite soaking wet, then add in the dry portland cement powder. I've used a drill mounted mixer, mixed it by hand, and have even pulled out the garden tiller, but It still ends a mish-mash of concrete consistencies. As a result, I think I end up using a lot more cement than is really needed.
The solution is to make a slurry of the Portland cement in water before mixing into the vermiculite. I fill a 5 gallon bucket about 2/3 full of the cement powder, then almost fill to the top with water. Then take a drill-mixer (pictured), and get all the cement suspended into the water. Then pour it into the moist vermiculite. At that point, I’m using a little electric garden tiller (picked up off a trash heap…took all of 5 minutes to find the loose wire that got it discarded)…but it can be mixed by hand with not much more effort. Doing it this way, I’m getting a uniform mix…
Since I started doing it this way, 90 pounds of Portland will bind up 12 cubic feet. That works out to about a 12:1 ratio by volume, which is a lot less cement than most are using. Less cement = higher insulation value.
Even though I have a more dilute cement mix, it seems to sets up fine… probably because of the more uniform distribution. Today I was walking on sections I poured yesterday and it supported my 225 pounds without leaving depressions.
Background story: Reason I use so much vermiculite is that I got it cheap (~$1.30 per cubic foot). Reason it was cheap is because I was able to buy a large amount (168 cubic feet) straight the mine where they make the stuff. Reason I got so much is that I wanted to get enough to insulate the bottom of the swimming pool this spring when I had to replace the liner. The pool project is now underway. After mixing up nearly 4 & 1/2 cubic yards of the vermicrete, I've finally stumbled on this better way to mix up the vermicrete.
For the pool vermicrete, I could have borrowed a neighbor’s concrete mixer, but the hassle of moving it down to the pool, and then having to go up and down the pool ladder with buckets of wet vermicrete didn’t seem worth it. Instead, put a wheelbarrow down in the pool and did all the mixing using the tiller. Today’s rain messed up my schedule but I should finish it tomorrow. Plan to have pizza party nest weekend and see if I can get some the guys to help put the new liner in exchange for food…
bad use of vermicrete roof thread
http://www.fornobravo.com/forum/f9/v...roof-3620.html
Problem I've had in the past always came in getting an uniform distribution of concrete mixed throughout the vermiculite. General method has always been to get the vermiculite soaking wet, then add in the dry portland cement powder. I've used a drill mounted mixer, mixed it by hand, and have even pulled out the garden tiller, but It still ends a mish-mash of concrete consistencies. As a result, I think I end up using a lot more cement than is really needed.
The solution is to make a slurry of the Portland cement in water before mixing into the vermiculite. I fill a 5 gallon bucket about 2/3 full of the cement powder, then almost fill to the top with water. Then take a drill-mixer (pictured), and get all the cement suspended into the water. Then pour it into the moist vermiculite. At that point, I’m using a little electric garden tiller (picked up off a trash heap…took all of 5 minutes to find the loose wire that got it discarded)…but it can be mixed by hand with not much more effort. Doing it this way, I’m getting a uniform mix…
Since I started doing it this way, 90 pounds of Portland will bind up 12 cubic feet. That works out to about a 12:1 ratio by volume, which is a lot less cement than most are using. Less cement = higher insulation value.
Even though I have a more dilute cement mix, it seems to sets up fine… probably because of the more uniform distribution. Today I was walking on sections I poured yesterday and it supported my 225 pounds without leaving depressions.
Background story: Reason I use so much vermiculite is that I got it cheap (~$1.30 per cubic foot). Reason it was cheap is because I was able to buy a large amount (168 cubic feet) straight the mine where they make the stuff. Reason I got so much is that I wanted to get enough to insulate the bottom of the swimming pool this spring when I had to replace the liner. The pool project is now underway. After mixing up nearly 4 & 1/2 cubic yards of the vermicrete, I've finally stumbled on this better way to mix up the vermicrete.
For the pool vermicrete, I could have borrowed a neighbor’s concrete mixer, but the hassle of moving it down to the pool, and then having to go up and down the pool ladder with buckets of wet vermicrete didn’t seem worth it. Instead, put a wheelbarrow down in the pool and did all the mixing using the tiller. Today’s rain messed up my schedule but I should finish it tomorrow. Plan to have pizza party nest weekend and see if I can get some the guys to help put the new liner in exchange for food…
bad use of vermicrete roof thread
http://www.fornobravo.com/forum/f9/v...roof-3620.html
Comment