  • Tscarborough
    replied
    Re: It is begun

    Pozzolans are a great gauging material if available.

    Leave a comment:


  • Nic The Landscaper
    replied
    Re: It is begun

    a far better thing to do than mess with the portland, lime, aggregate ratio is to add about .25 parts of a pozzolan to the mix. Pozzolans speed up the reaction process of the lime, extend the life of the portland cement and add initial hardness themselves. It is one of the many things I add to my concrete spec mixes for almost everything now.

    Leave a comment:


  • Tscarborough
    replied
    Re: It is begun

    As a rule, 10% is considered the max for gauging material. For plaster or anything similar I would not use more. For a compression structure, the mortar acts mainly to hold the units apart and won't fall out unless mechanically disturbed, so 20 to 25% Portland cement by volume of the cementious materials is not a problem.

    Leave a comment:


  • GianniFocaccia
    replied
    Re: It is begun

    Thanks for the explanation, Tom. Makes me feel a lot better since I opted for an 'old world brick' look to the inside of the dome rather than the 'mortarless stacked brick' look.

    Two questions then:

    Given portland's initial-set benefits and lime's cementious qualities, can the 3-1-1-1 proportions be tweaked to reduce portand's refractory weakness?

    What is the difference between brick dust and fire (mortar) clay?

    I am continually amazed at the amount of knowledge you have and readily share.

    Thanks a million,

    John

    Leave a comment:


  • Tscarborough
    replied
    Re: It is begun

    Below 20% the portland acts as a "gauging" agent, not the primary cement. It is used for a rapid enough set to allow the work to proceed. Lime is an excellent cement, but it does not have an initial set. It hardens over time by the process of absorbing carbon dioxide from the air, and thus something has to be added to give the initial set.

    If it was readily available, brick dust is a better choice as a gauging material, and when I have it, that is what I prefer to use for lime mortars/plasters.

    Leave a comment:


  • david s
    replied
    Re: It is begun

    That's what the lime in the mix is for. If the Portland cement fails the lime takes over as it can handle the heat.

    Leave a comment:


  • GianniFocaccia
    replied
    Re: It is begun

    Tom,

    Now you got me scared. The joints facing the inside of my oven are approximately 3/16" and made with 3-1-1-1 homebrew mortar. With this recipe, the portland comprises 16% of the mix. Exposed to direct flame, how long will it take for this mortar to disintegrate and eventually fail?

    John

    Leave a comment:


  • Tscarborough
    replied
    Re: It is begun

    500 sustained degrees will cause the portland cement matrix to disintegrate. Direct flame will cause spalling, sometimes explosively. I have burned the grill quite a few times and measured the heat in that area, and it remains below 400 degrees.

    Leave a comment:


  • splatgirl
    replied
    Re: It is begun

    Being the guru of all things concrete and masonry tscarborough, do you have any idea how much heat can be applied to part of a (thinish) concrete slab before it spalls or cracks? Your grill/countertop proximity is similar to one of my kitchen tops which is next to my 130,000btu commercial wok burner gets too hot to touch if I'm using the wok for any period of time. It's been fine over the six years it's been in use, but I figure some day it's going to object.

    Leave a comment:


  • Tscarborough
    replied
    Re: It is begun

    Derk, that is where the sink goes. I cut 95% of the cement board in the cutout, so I just have to make a few cuts and it is open to the bottom.

    Leave a comment:


  • GianniFocaccia
    replied
    Re: It is begun

    Note to self: Next time do not make the oven usable until everything else is finished.
    Tom, I disagree Why go to all the trouble of a 4-hr dome build and not be able to use it right away? You could have easily thrown a couple of pork shoulders in your finished oven at 228F and in the ten hours it takes to create pulled pork have the counters and tops built, poured, polished and sealed.

    John

    Leave a comment:


  • Derkp
    replied
    Re: It is begun

    Tom,

    What goes in the cutout under the medalion?

    Derk

    Leave a comment:


  • ggoose
    replied
    Re: It is begun

    Those countertops look great. I am guessing you poured them in place. With what will you grind them? I am considering a concrete top for my build, though I need to research the process a bit first.
    gene

    Leave a comment:


  • Tscarborough
    replied
    Re: It is begun

    Well, it took a year or so, but I finally poured the countertops (they will dry to the same color as the wall). I will grind them down a bit, and move on to the pergola. I still need to caulk and paint the damned oven for that matter. Note to self: Next time do not make the oven usable until everything else is finished.

    Leave a comment:


  • Tscarborough
    replied
    Re: It is begun

    Have you seen anyone build a complete Pompeii dome in 4 hours? I was talking about the arch, not the oven.