    About to start the block stand tomorrow - If I use mortar to level the first course of blocks, do I have to wait a day for the mortar to harden before laying on the second? Or can I stack all 4 courses in one day?

    If I get the first course leveled correctly, does this mean I won't need mortar to level the other courses?
    Here's mine:
    http://www.fornobravo.com/forum/f8/j...man-15992.html
  • GianniFocaccia
    Il Pizzaiolo
    • Jun 2009
    • 1645

    #2
    Re: wait for mortar to harden?

    The mortar will harden sufficiently for you to keep going as long as there is daylight.

    Comment

    • brickie in oz
      Il Pizzaiolo
      • Mar 2009
      • 3445

      #3
      Re: wait for mortar to harden?

      Originally posted by jimkramer
      About to start the block stand tomorrow - If I use mortar to level the first course of blocks, do I have to wait a day for the mortar to harden before laying on the second? Or can I stack all 4 courses in one day?
      You can lay as many courses as you like, we generally go to 8 courses, then it gets too high to lift the blocks.

      Originally posted by jimkramer
      If I get the first course leveled correctly, does this mean I won't need mortar to level the other courses?
      No, there are specific blocks that are made to dry stack, even then they require a tweaking with a plastic wedge to get them level(ish) and plum(ish) but these blocks are made to be core filled with fine concrete and rebar to stabilize them.