Announcement

Collapse
No announcement yet.

Curing

Collapse
X
 
  • Filter
  • Time
  • Show
Clear All
new posts

  • brickie in oz
    replied
    Re: Curing

    Originally posted by david s View Post
    There is confusion about the term "curing".
    Firstly, when applied to freshly laid concrete containing Portland cement: it should be kept moist for a week. Concrete not treated this way will not achieve its max strength. This applies to anything made containing Portland cement. It is impractical in many instances to keep a slab moist for a week, so it is often not done, however the resulting strength may be down as much as 60%.
    Please tell me the AS standards this is referring to so I can reference it.

    I havent seen this anywhere in the brickwork AS or the concrete AS and I have both at hand.

    Did I miss something in the AS's ?
    Last edited by brickie in oz; 04-16-2011, 02:47 PM.

    Leave a comment:


  • david s
    replied
    Re: Curing

    There is confusion about the term "curing".
    Firstly, when applied to freshly laid concrete containing Portland cement: it should be kept moist for a week. Concrete not treated this way will not achieve its max strength. This applies to anything made containing Portland cement. It is impractical in many instances to keep a slab moist for a week, so it is often not done, however the resulting strength may be down as much as 60%. Castable refractory containing calcium aluminate cement does not need this treatment. It should be covered for 24 Hrs only.
    The other type of "curing" referred to with oven construction is the elimination of water. This is a problem because steam pressure build up can cause cracking and moist insulation doesn't work too well. We should really invent another name for this process to avoid the resulting confusion.

    Leave a comment:


  • brickie in oz
    replied
    Re: Curing

    Originally posted by PlanoPhil View Post
    Wow my head is hurting from reading all the opinions on curing. Keep it wet? What's that all about? I thought the whole idea was to get the moisture out. Confusing.
    Anyway I'm about to install my Casa 90 and need to know:
    Keeping it wet is a urban myth about letting the mortar dry slowly so it hardens properly without cracking.
    Ive laid bricks on 40c days and honestly havent seen any cracking or weak joints.

    They pour large concrete slabs for houses in the heat here and they dont even crack, well, not more that you would expect.

    Originally posted by PlanoPhil View Post
    1. Can I cure before applying the insulation blanket?
    2. Should I cover it if it rains?
    3. How will I know it is cured sufficiently?



    1.
    Yes and it would dry quicker doing it that way.

    2.
    Yes, otherwise you are right back to where you started from.

    3.
    Youll know, because the fires will actually start to get hot and burn with a passion.

    Leave a comment:


  • PlanoPhil
    started a topic Curing

    Curing

    Wow my head is hurting from reading all the opinions on curing. Keep it wet? What's that all about? I thought the whole idea was to get the moisture out. Confusing.
    Anyway I'm about to install my Casa 90 and need to know:
    1. Can I cure before applying the insulation blanket?
    2. Should I cover it if it rains?
    3. How will I know it is cured sufficiently?

    Thanks
Working...
X