    Use just heat stop 50 for shell construction

    Hello I'm new to the forum but I've been here looking for a few years finally gonna start the build, I'm a concrete floor guy so I'm not worried about the stand so much as the oven construction it's self I want to build the forms and then use the heat stop 50 over this ? First question is
    Do I mix he heats top 50 with anything other than water ( rock , sand, fiber etc)
    Second question
    How think do I make the walls and do I cover the form in sections or do I install the refractory in one go?

    Thanks
  • vtsteve
    Apprentice
    • Jan 2010
    • 110

    #2
    Re: Use just heat stop 50 for shell construction

    Are you planning to use the Heatstop 50 as a castable refractory? It's intended for thin bonds between firebricks, not as a bulk refractory. It's also more expensive than a true castable refractory. It might work if you used crushed firebrick as aggregate, and the usual stainless needles for reinforcement, but it's probably not the best way to go.

    Comment

    • david s
      Il Pizzaiolo
      • Mar 2007
      • 9209

      #3
      Re: Use just heat stop 50 for shell construction

      Go to a refractory supplier, tell them what you are doing and make sure you get a dense castable refractory not an insulating one.
      Kindled with zeal and fired with passion.

      Comment

      • Fiano
        Serf
        • Aug 2014
        • 13

        #4
        Re: Use just heat stop 50 for shell construction

        I went to the local supplier here in town asked about the crushed fire brick to use as aggregate they don't make the fire brick so that was a no go so at $1.48 per brick and $44.50 per 50lbs of heat stop 50 II IM going the fire brick route

        Comment

        • deejayoh
          Il Pizzaiolo
          • Jul 2010
          • 1893

          #5
          Re: Use just heat stop 50 for shell construction

          I was going to say that heatstop sounded like an expensive way to go, but I see you already figured that out!

          Do some research on home-brew for your mortar. It will save you some more money
          My build progress