Thanks Tex...It's been along time coming.. my backyard isn't all that big and that corner sits at a 45 degree, and about 5 steps, to my kitchen. Perfect outdoor kitchen location and I have been using it in it's unfinished state quite a bit so far this summer. Perfect for a fish fry, searing, soon to be pizza/roasting, etc....
So I'm putting down my dual layer split floor with a dry mix of 1:1 fire clay/sand and tapping them with a rubber mallet. Seems to be working well and my thoughts are either 1. the moisture from the vermicrete layer will harden the dry mix or 2. I'll wet polish the 2nd layer and let the water from that set the base, any thoughts on that are more than welcomed.
Also, going to use the dry mix in between the split layer to level...gotta do something.. thank god for the alphabet and numbers..roman numerals just wouldn't work for me
Last edited by cnicholson; 08-22-2012, 09:13 PM.
Reason: forgot pics
Ok...my first course + w/ the dome... a couple of things.. I am using the homebrew mortar method. When we did our remodel I used it to transition the clay/brick chimney to a duravent (per the duravent installer recommendations) and it seemed to work well.
So, I'll admit it's not the first time I have put mortar to a brick- it's my second, but it's the first time I've ever taken it seriously or expected it to hold in a fire raging at 1000 degrees so I'm a little paranoid about doing it right. My questions at this point are:
1. Can I go back and pack the areas that are light on mortar and get satisfactory results?
2. I got a little too excited with the first 7-8 bricks (yeah..you guys know what I'm talking about) and forgot to soak them in water before I mortared them. I did notice the bricks draining the moisture out of the mortar real quick.. Should I go back and reset these? My though is NO because they are really held in place by gravity?
3. I remember reading an article on chimneys once and it said the biggest fire hazard was a gap in the mortar. Does this hold true on the dome (or WFO as a whole) as well? I'm learning as I go how much mortar to put with the trowel and where but I know my first rodeo ain't looking pretty...
I'm going to have to get a good signature quote to use at his point..
1. Should be able to point and tuck your home brew into joints needing more mortar.
2. Soaking the brick allows you more time to work the placement of the brick. Move on if your aligment looks good, but soak your brick from here on!
3. Les did a mortarless build..... your will be point and tucking your joints anyway.
Good luck, interested to see how splits work out for you.
Alrighty... I started reading through a few threads and I'm starting to get a little nervous that I'm doing crappy work here..but I think it looks good?!? It seems to be going faster than alot of peeps out there (I have probably spent a total of 4-5 hours putting the dome bricks up so far) and it's dead level. I didn't even think about checking it but my IT started flexing out of it's cradle so I thought I better check it.
My hope is that because I'm using splits, they do indeed set faster and as GF said they are easier to "eyeball" in place if need be. Also the joints are not a big allowing the mortar to set stiffer and quicker so I can press against the set brick a little for alignment on the next one?!?!
Either that or I am going to end up with a pile of rubble in a few days..
Don't wish for your mortar to set too quickly! It'll kill the mortar and it'll be as weak as sand. The second photo seems to show it is in fact going off too quickly, with the mortar showing signs of shrinking back off the bricks. This is the suction drawing the water from the mix. Before each course/chain you'll be better off soaking the bricks for 30 seconds in a bucket of water, take them out and then set them aside. Allow the bricks to sit for a further few minutes until any water has gone from the face of the bricks before using them. This'll control the amount of water the brick want to pull from the mortar. The mortar will dry slower. Just work slower. Then, if its warm, spray the laid bricks occasionally with a pump hand sprayer and cover with dampened hessian or any other cloth when the days work is complete. You must give the mortar enough time to "cure" not force the drying process.
Look at the spots of mortar that are on the floor of the oven, they'll crumble to dust in your fingers. This is what the joints could do, if they dry out too quickly.
Last edited by Bookemdanno; 09-04-2012, 05:40 AM.
Reason: smelling pisstakes
Judging from the looks of your mortar, it was mixed a little dry and even though you're in cooler San Diego county, the bricks were hot enough to suck all the moisture out of the mortar quickly. This same thing happened to me originally. I would recommend mixing your mortar more wet to the point that you can literally 'press' your bricks into place with the pressure of your hand. The mortar should squeeze out (which you can recover), but you will soon learn to apply the right amount to limit this. Ideally, you don't want to move the brick once it has been pressed into place. I would also lightly (not soak) spritz your brick with a bottle sprayer so that the mortar bleeds into the brick and make a solid bond.
John
Agree with GF and bookem, your mortar appears to be separating from the bricks. If you give one of them a soft knock with a rubber mallet from the back, I bet it breaks loose. The bricks should be solidly attached w/in a day.
I do like that sunken IT. Perfect for getting a low dome! Splits are clever too.
I was definitely afraid of the mortar pulling away from the bricks. I went around the whole thing and gave it a decent whack w/ the mallet and nothing popped loose. I also grabbed some spots off the floor and they were hard- no crumbling. I saw a stucco wall one time go off and the guy brushed the wall with pushbroom to remove it, I am assuming that is the crumbly you speak of bookem?. Nonetheless, should I take it down and start over or just do better w/ the next courses? I actually started soaking the bricks for 2-3 minutes and when I take them out they seem like they want to suck in more water, weird!
GF- I will mix my mortar a bit runnier for sure. As of right now I can set my bricks by hand, maybe a hammer fist here and there and it I will ooze. The thing is that those bricks are sucking the moisture right out of the mortar so I think if I get more water in there I'll be OK.
DJ- The splits were actually a product of economics in my case, seconds at $.25 per brick, but I too like the way it's shaping up. I'm hoping to have a lower than hemispherical dome, and I think it will end up that way, but I'm not going to have an issue with it if not, just hope my opening size isn't too out of whack.
Hopefully I have some more time in the next few days to spend on this puppy.. Thanks again for all the advice!!
GF- I will mix my mortar a bit runnier for sure. As of right now I can set my bricks by hand, maybe a hammer fist here and there and it I will ooze. The thing is that those bricks are sucking the moisture right out of the mortar so I think if I get more water in there I'll be OK
If your mortar is oozing, you're good. 2-3 minute soaks is too long (real masons reportedly don't wet their bricks at all, I'm guessing it's all in the mortar), plus it adds to your build (soaking) time. I just kept a water bottle handy and sprayed the brick sides and bottom, buttered it up and pressed into place.
Getting a slightly lower dome won't be difficult at all. I used a plywood dome template (no IT) to set the angle of the first brick on each course and just stayed with that angle all the way around. I might've checked for angle consistency every 5-6 bricks, but it was easy to make minor adjustments.
My son is attending UCSD. If you don't mind, I'd love to stop by one of these weekends when I go down to watch him compete (he's on the swim team). Would really like to see your dome progress since it promises to be one of the best-looking ovens on the site!.
John
Stone and brick are different materials, with different methods and levels of suction to deal with.
Firebrick will definitely need a dunk, you'll see millions of bubbles escaping but 30 seconds or so will suffice. Like i said, you want no surface moisture when you come to laying the brick or it'll cause the mortar to stain the face of the brick and dilute the actual mortar at the face of the brick as the fines (cement/clay) will bleed from the aggregates.
if those bricks you've laid are still there, i'd carry on regardless and just adopt the new method. But i'd spray the laid bricks first to control the suction from them to the new mortar.
Your mortar should be wet enough to allow you to simply press and wiggle your brick into place. Make sure you mix it for as long as you can to get it good and fatty, and don't add too much water too soon. A good test is to take some onto your trowel, and tap it against the bucket once to settle it then invert the trowel. It should stay there. Think "cake mix", not dough.
Last edited by Bookemdanno; 09-07-2012, 01:47 AM.
Reason: more info
Very good analogy for us lay folk...batter not dough. Thanks! I mixed up another batch today and laid some more. I'm telling the truth when I say that
1. I soaked my bricks for about 1 minute
2. My mortar was mixed to the consistency of a batter, I slapped the trowel on the end of the bucket and it settled right on there like I think it should (I've seen masons work and had my fill of youtube videos!).
And sure enough it seems as though the mortar is pulling from the brick. I'm using the homebrew method with 1:3:1:1 ratio. I started using silica sand because I used it for the clay/sand leveling medium and switch to a washed plaster sand. The only thing I can really think to do it soak them AND spray them just before they get laid.
GF- Congratulations on being a UCSD dad! Their aquatic dept is pretty respectable in the collegiate world if I remember correctly? That place has come a long way from some old buildings in a Eucalyptus grove when I was a kid..freaking palace now!! Your are more than the stop by anytime, my schedule is all over the place so just let me know and we'll see if it works!
A caveat- my dome is pretty photogenic. It might look like one of those Hollywood types who you wouldn't recognize in person because they don't have makeup on!
Comment