**Update**
Today I leveled the cooking floor with a slurry mix (sand & fireclay). It ended up taking a lot longer than expected because I realized that I didn't have a perfect circle for the cooking floor

Moved on to starting the first course

I laid out the first course as rowlocks instead of headers. If I did them as headers the bricks were only going to be 3/4" above the cooking floor; as rowlocks they are 1 1/2" above the floor. This won't cause any issues in the future will it? I can change to headers if that's the better option. Just need to know before I start the second course. I have no issue with starting over at this stage; easier now vs extremely hard further down in the build...