    Hi all, new ambitious oven owner here.

    I am going for a pretty standard hemisphere-on-a-row-of-soldiers design, but i have to admit I hit a bottleneck when it comes to brick sizing, in regards to the resulting joint gap.
    The overall goal is to avoid multiple and angled cuts on the bricks. So, for the square-cornered bricks, on the interior of the dome i will just get them to touch at one corner and then the resulting joint gap won't be more than 3mm (1/8 in), that's the easy part.

    But what grinds my gears is how big should I allow the joint gap to be on the exterior side, considering the overall joint bond strength and thermal-shift behaviour.

    Naturally going upwards towards the top rings of the dome the width of the brick must shorten, as to reduce the joint gap (both on the inside and outside of the dome), but what is the absolute threshold I should aim for? Does a rule of thumb exist? I guess it is eventually mortar-brand dependant and on the very top rings beveled bricks are inevitable, but like i said the goal is to minimise brick cutting so to cut only when necessary, i.e. max joint gap reached.

    Extending already on the matter, shortening the width of the brick also reduces the brick overlap - staggering margin. I know that the brick joint of the next row should ideally sit in the middle of the the brick in the row below, but we all know that this is impossible to maintain, hence the use of custom stagger-bricks here and there, but what is the minimum overlap of bricks from row to row we aim for? you get it, since making stagger-bricks means performing cuts.

    I am surprised that a thread somewhere doesn't exist already, or if I didn't find it please refer me.

    Thanks all.
    Last edited by Al Neer; Today, 12:35 AM.

  • #2
    Welcome to the forum Al! Many of us simply use or homebrew or mortar to fill those outside gaps. The dome build/structure is extremely sturdy and the gaps between the bricks on the inside are minimal...and that's all you're really aiming for. Some builders use shims or wedges to hold the angled bricks but usually you butter each brick with enough mortar to bond and hold it in place as the build progresses. Use any left over mortar from each chain to backfill. I built my dome and then filled remaining gaps with mortar before applying my outer dome insulation.

    Wetting each brick (some folks just drop them into a bucket of water) prior to using them is important so the brick doesn't draw moisture from the mortar too quickly (or at all ). That way you get the best bond possible. As you have noted, the heat cycling of the normal oven use WILL crack some of the mortar joints. The important thing is to stagger joints between each chain (layer) of bricks so you don't have a crack develop going up through several chains via the "aligned" joints. Even with that visual, scary type of crack, the dome structure will be fine and the Cracks will dissappear when the oven cools down. In fact, before our modern methods of determining when our ovens had reached proper temps...old school simply noted the size of cracks indicated the oven was hot enough for the upcoming bake.

    I didn't angle cut any bricks for my 39" dome and simply filled the outside gaps before insulating...finished in 2009, still standing & functional Relax, don't grind your gears!
    Mike Stansbury - The Traveling Loafer
    Roseburg, Oregon

    FB Forum: The Dragonfly Den build thread
    Available only if you're logged in = FB Photo Albums-Select media tab on profile
    Blog: http://thetravelingloafer.blogspot.com/

    Comment

    Working...
    X