  • UtahBeehiver
    replied
    Take Dave's advice seriously. One of the most common reason an oven performs poorly is due to wet insulation, either left over from the build, IE pcrete mix, or water ingressing in and getting the insulation wet (water will find a way in). A way for water to egress has proven to be an insurance policy for us builders.

    Leave a comment:


  • david s
    replied
    Originally posted by IH123 View Post
    I am not going to create weep holes, I can wait as long as it takes for the slab to dry, same for perclite layer, here in Calgary humidity is always low except when there is downpour. its more important for me to keep the slab moist for at least 28 days so it can resist harsh winter frost heave and cracking, I have to design the oven to shed its moisture not through holes in slab, may be sideways
    Ok. 28 days damp curing is the industry standard, so yes, take your time and keep it covered for that long. If you are pouring your own vermicrete slab, be aware that there is a very large volume of water required in the mix, much of it is left as free water after the hydration process has chemically taken up what it requires, so extended drying is important before building over it and locking it in. Take a read of my attached experiment on drying a vermicrete slab.

    Vermicrete insulating slab copy.doc.zip

    Leave a comment:


  • IH123
    replied
    I am not going to create weep holes, I can wait as long as it takes for the slab to dry, same for perclite layer, here in Calgary humidity is always low except when there is downpour. its more important for me to keep the slab moist for at least 28 days so it can resist harsh winter frost heave and cracking, I have to design the oven to shed its moisture not through holes in slab, may be sideways

    Leave a comment:


  • david s
    replied
    Weep holes cast into the slab?

    Leave a comment:


  • IH123
    replied
    Click image for larger version

Name:	IMG_8749.jpg
Views:	211
Size:	1.30 MB
ID:	471410just finished the pour around 12:30pm, 2 hours ago, likely have to wait few hours before finish as 6 hours set delay makes it soft still
    Attached Files

    Leave a comment:


  • IH123
    replied
    Click image for larger version

Name:	IMG_8727.jpg
Views:	215
Size:	365.9 KB
ID:	471393 Click image for larger version

Name:	IMG_8728.jpg
Views:	193
Size:	785.4 KB
ID:	471394The arch plywood forms

    Leave a comment:


  • IH123
    replied
    Click image for larger version  Name:	IMG_8735.jpg Views:	0 Size:	1.35 MB ID:	471391

    small change in the plan, instead of PVC pipe cut, I cut the rebars at corners so when corner is trimmed they wont be closer to it than 2", I use plywood pad to dampen the corner edge and when slab is cured I will use angle grinder or concrete saw to trim it proper a tiny. my next step is the pour of the slab, will be using 6 hours of set delay: for 2 30kg 4000psi ready mix, I will use 3gr of air entrain, 45 gr of set delay (all fritz pack) , and 20 grams of 1" poly fibers. I will vibrate with my 35mm concrete vibrator. next update is after top slab is poured and finished. have 34 bags to mix and doing it all by myself in the morning
    Last edited by IH123; 06-04-2026, 11:24 PM.

    Leave a comment:


  • UtahBeehiver
    replied
    Serious steel in there.

    Leave a comment:


  • IH123
    replied
    Click image for larger version

Name:	IMG_8707.jpg
Views:	225
Size:	914.9 KB
ID:	471348

    Today's work: grouted all cores leaving about 2" on top without grout so the slab would cap on it when poured. used 3 gram fritz pack air entrain + 15 grams fritz pack set delay per 2 30kg ready mix bags (4000psi) and about 5.6 litres of water (more than minimum to keep grout fluid), I vibrated with the concrete vibrator too, installed the top slab rebar mat

    Leave a comment:


  • Giovanni Rossi
    replied
    Originally posted by IH123 View Post

    why? straps are better than stakes ?
    It's all good. Staked bracing will work fine. I couldn't see the back and it doesn't look like you have the angle to stake and brace the front with that hard patio in the way. I just know that sometimes guys underestimate the horizontal force that thickness of concrete can exert on the form. I'm not honestly sure if the nails in the front will prevent the top of the board from flexing outward. Even if it does, would it be significant??

    As far as strapping, as long as the blocks in the center of the boards of the form are proud of any other blocking, the pressure points will be on the corners and the center blocks. You obviously don't want to tighten the straps such that you're deforming the boards inward.

    To answer your other questions. :

    I drilled into my slab on grade and glued rebar into the holes. The CMUs are dry stacked round those rebar. I filled the cores with concrete to a level about 4" below the top of the CMUs. Then put a 90 on the rebar and those legs are tied to the rebar in the top slab. The concrete pour finished filling the CMUs and formed the slab.

    It looks like you have plenty of vertical support for the overhang of your slab. I banded the supports on mine because I have a really awkward site and I was afraid I would kick one of them out as I worked the concrete. I wasn't concerned about the ones in the front under the cantilevered section because I felt there was so much weight there that those legs weren't going to budge.

    Looking forward to the rest of your build.

    Leave a comment:


  • IH123
    replied
    Originally posted by Giovanni Rossi View Post
    ​If not already in your plan, you may want to consider center supports on the sides. Strap and blocks are one option,
    why? straps are better than stakes ? the only place I don't have stakes is the front however I have inserted 3" nail through bottom workform and into the edge so edge can't push out ( nail shear) , and to protect legs from slipping outwards I used small stakes for them. rear, and sides I can have as many stakes as needed. my worry about straps is the don't have enough tension at the middle of the lumber, and if I use very strong banding then the form could be twisted.

    The picture shows cmu blocks dry stacked (or may be glued?), I had mine mortared with type s mortar and staggered pattern so only risk of leg/stud shifting is bowing under weight , I have more of them to compensate.

    do you think its serious to have that support on the studs/legs? because if so I could just have a long lumber joining them together and then put another shorter set of stakes for them too
    Last edited by IH123; 05-30-2026, 10:09 PM.

    Leave a comment:


  • IH123
    replied
    Originally posted by david s View Post
    Because all concrete is somewhat porous you may want to consider adding a waterproofing additive to the concrete for the supporting slab, I use Xypex. Water wicking up from the base can find its way into the inner parts of the oven where it can become problematic and difficult to remove. This is highly weather dependent of course, but never allow sprinklers against the stand for this reason. Another solution to this problem is to paint a sealer over the top of the supporting slab, but I have no idea about its longevity or how a sealer would stand heat.
    30 x 30 kg is a lot of hand mixing, have you compared readymix pricing? You should be able to pour the cores and slab top in one go.
    1-moisture could go up or down and the more dams I put the more focused and damaging it would become, I think I will just leave it natural for now (no vapour barrier on top slab) and would have to protect the site from downpour, rain, snow, and ice melts- I will not manage gaseous level moisture. its my first build and as long as a risk is not of high impact I will ignore it for the sake of completing and hoping the solution can be made after a problem occurs (only for low impact risks)
    2-I already have the 60 bags (4000psi) in my garage wrapped with vapour barrier above ground, I have bought used 4 cu ft drum concrete mixer. I did mix 28 25kg bags for my bottom slab (6000 psi with fibre) so 30 30kg 4000psi bags wont be different. I will pour the grouts first and then after a bit of cure the top slab (not both at same time, too risky for leaks and blow outs)

    Leave a comment:


  • Giovanni Rossi
    replied
    ​If not already in your plan, you may want to consider center supports on the sides. Strap and blocks are one option,

    Leave a comment:


  • david s
    replied
    Because all concrete is somewhat porous you may want to consider adding a waterproofing additive to the concrete for the supporting slab, I use Xypex. Water wicking up from the base can find its way into the inner parts of the oven where it can become problematic and difficult to remove. This is highly weather dependent of course, but never allow sprinklers against the stand for this reason. Another solution to this problem is to paint a sealer over the top of the supporting slab, but I have no idea about its longevity or how a sealer would stand heat.
    30 x 30 kg is a lot of hand mixing, have you compared readymix pricing? You should be able to pour the cores and slab top in one go.

    Leave a comment:


  • IH123
    replied
    Click image for larger version

Name:	IMG_8673.jpg
Views:	165
Size:	782.3 KB
ID:	471244 Click image for larger version  Name:	IMG_8675.jpg Views:	0 Size:	631.5 KB ID:	471243
    I finalized the workform today and sealed the gaps with window and door expanding insulation foam, will trim excess after it cures. next will be waiting for good weather to grout all the cores with about 30 30kg bags adding air entrain admix:
    Last edited by IH123; 05-29-2026, 06:15 PM.

    Leave a comment: