Hi all,
I'm hoping to pour here in the next few weeks, thanks all for participation on this forum, it's invaluable!
Here's a thought. I'm considering a truck pour in a few weeks. How outrageous would it be to have the foundation slab _and_ hearth base poured at the same time?
I'm planning to frame the hearth base, resting it on 4 x 4s on the ground nearby, where I'll screed, finish, level and cure......A couple (?) weeks later I'll use my front end loader to web sling it onto my block supports?
It'd be a gentle operation but I feel it could be done properly and safely with a few extra bodies....
I see a possible savings of several hours and it takes advantage of having the truck in place.....once....., as a newbie I should ask: ."...what am I missing here?"
I'm hoping to pour here in the next few weeks, thanks all for participation on this forum, it's invaluable!
Here's a thought. I'm considering a truck pour in a few weeks. How outrageous would it be to have the foundation slab _and_ hearth base poured at the same time?
I'm planning to frame the hearth base, resting it on 4 x 4s on the ground nearby, where I'll screed, finish, level and cure......A couple (?) weeks later I'll use my front end loader to web sling it onto my block supports?
It'd be a gentle operation but I feel it could be done properly and safely with a few extra bodies....
I see a possible savings of several hours and it takes advantage of having the truck in place.....once....., as a newbie I should ask: ."...what am I missing here?"






Would not a poured mix be very close in weight?...I'll call the delivery guys and ask that one...) 80# bag of Sakrete is .6 cu ft… 12 cu ft would require.20 bags = 1600 lbs + rebar…. I’m thinking 5/8”, probably 5- 6ft pieces and 5 -7’ pcs for a total of 65 ft @ 1+ lb / linear ft = 70 #
Comment