Currently in the build process for my new oven. Ordered a Premio2G 120 and picked it up at the Forno Bravo factory.
I have the slab done and the block stand is almost ready for the top slab. I'm filling every other core with rebar and concrete. The holes that are not filled with concrete.. what do you guys block those with so that when the slab is poured it doesn't go down the holes? I was thinking about using squares of wood or rigid insulation to block them up.
I have the slab done and the block stand is almost ready for the top slab. I'm filling every other core with rebar and concrete. The holes that are not filled with concrete.. what do you guys block those with so that when the slab is poured it doesn't go down the holes? I was thinking about using squares of wood or rigid insulation to block them up.





) After the concrete has set, run a drill up the plastic pipe from the bottom. It will pop out a small crater at the surface of your hearth...providing an excellent little well for any excess water that gets in under the oven perimeter to collect and find an exit through the weep hole. A little insect screen material placed over the base of the hole with silicone will keep any bugs from finding a new "home".
.)
Comment