Well today, I finally got started on my WFO. I cut the soldiers and made a layout of my floor plan. The concrete truck finally showed up today and I got my slab poured. I have had my concrete on order for two weeks finally I called another company today and they said they can bring it this afternoon. Here are a few photos of my progress let me know what you think and if there is anything I should change let me know. I ordered the Harbor freight 10” saw $199.00 I had a 20% discount coupon. I sure do like it cuts like a dream.
Huck
P.S. One more photo in nex post.
Huck
P.S. One more photo in nex post.






I got quite a bit done on my pizza oven stand. I mixed and poured 20 bags of Concrete and failed all of the concrete blocks. And frame the bottom tray and installed rebar. Tomorrow I hope to be able to frame it out with 2X8 and be ready to pour the final slab Monday.
Comment