42" Build Underway in Central Alabama
Collapse
X
-
Re: 42" Build Underway in Central Alabama
Laid the floor today. This was more difficult than I expected - primarily because of slight variances in size from one fire brick to the next. I ended up with a few gaps that are a bit wider than I would have preferred. But I don't think I was left with anything that a peel would catch on!


Testing the fit of the dome first course:

Comment
-
Re: 42" Build Underway in Central Alabama
Looks great!
You will be in spec without it but, some calsil under your floor will improve your oven floor performance
.
Joe Watson " A year from now, you will wish that you had started today" My Build Album / My BuildComment
-
Re: 42" Build Underway in Central Alabama
With a herringbone floor, 1/4" differences will not cause an issue, and any gaps will fill with ash. Looks great!Comment
-
Re: 42" Build Underway in Central Alabama
Forgot to mention that I had a couple of high spots on the vermicucrete surface. I took them down with a diamond cup on a side grinder. It took almost 2 seconds! I was very surprised at how well the vermicucrete machined - and how good it looked after grinding.Comment
-
Re: 42" Build Underway in Central Alabama
If you used a grinder on vermicrete and did not destroy it you may have used too stiff a mix. What was the ratio you used?Comment
-
Comment
-
Re: 42" Build Underway in Central Alabama
Probably not, if they are "set". But, they should be just laying there sort of "free-floating".
I didn't mean to alarm you. 4" of vcrete is in spec, without additonal insulation underneath the floor. It is just a matter of choice. Some of us have added insulation under there to the point of diminishing returns
.
Joe Watson " A year from now, you will wish that you had started today" My Build Album / My BuildComment
-
-
Re: 42" Build Underway in Central Alabama
G'dayThanks to all for your replies and encouraging words!
"technically perfect" probably won't be achieved in our build - but it's a great goal! I think our oven will be "family perfect"...and I am looking forward to the times we can use it. And, by the way, my wife and all three of our teenagers have been involved so far - they just haven't all made the photos. Yes, it has been hard but fun work so far...
I like that term " family perfect" I recon it should be used more often
Regards DaveMeasure twice
Cut once
Fit in position with largest hammer
My Build
http://www.fornobravo.com/forum/f51/...ild-14444.html
My Door
http://www.fornobravo.com/forum/f28/...ock-17190.htmlComment
-
Re: 42" Build Underway in Central Alabama
Another update with a few more photos of progress. Summer has become more busy and I've had less time to work on the project - but I have started making mortar (1:1:1:3 recipe) and laying a few brick.
I forgot to account for my cardboard spacer (covered with blue painter's tape) adding to my floor diameter:

Floor with first chain:
Comment
-
Re: 42" Build Underway in Central Alabama
I started off with an IT made from 1/4 all-thread and a small tripod ball head (later discovered that Hendo's original tool used a tripod head). I was very happy with it until I realized that it would work great on the first couple of chains, but then start adding unnecessary height as the chains got higher and higher - eventually adding about 2" to the upper chains.
So I redesigned the pivot end of my IT using a padlock hasp/hinge. I also used epoxy and a large fender washer to add strength to the Masonite:

My IT and folding Masonite template (shimmed in place due to cardboard spacer around floor brick):
Comment
-
Re: 42" Build Underway in Central Alabama
Hey looks like things are going well so far with block. May I ask were you getting refractory goods? Do you have a place in your area? Down here in LA, lower Al tough time getting any light motar and other goods. Could you lead me in the right direction. I have slab down and waiting for end of summer to start block and brick. Good luckComment
-
Re: 42" Build Underway in Central Alabama
I live near Tuscaloosa and got my fire brick and fire clay at Willcutt. I'm making my own 1:1:1:3 mortar, and so far I like it. The only high heat mortar I could find in the area was Firerock (it is actually called an adhesive - for modular fire places. It is polymer based, which made me nervous).Hey looks like things are going well so far with block. May I ask were you getting refractory goods? Do you have a place in your area? Down here in LA, lower Al tough time getting any light motar and other goods. Could you lead me in the right direction. I have slab down and waiting for end of summer to start block and brick. Good luck
I am actually from LA (Jackson - Clarke County). Where are you?Last edited by edsiajb; 12-10-2014, 10:49 AM.Comment





Comment