I've done it: No longer a poser or forum lurker, I've actually made real progress! I would not have had the confidence if it were not for all you forum members I've asked questions to or read up on your ovens or advice.
I have dug footings, installed rebar and poured my foundation for oven base.
Here are some stats on what I've done and why:
4 1/2 concrete blocks wide by 5 blocks deep. (those are 8x8x16 CMU concrete blocks. That's a pad I framed out at 82"x76"
It has 12" wide footings and 16" depth with the center pad area at 4"-5" deep with 1/2" rebar at the bottom (2), top and approx 12" squares across the top. All was placed on 2" dobee blocks to lift it off the ground.
It came to 1 1/2 yards plus 2 60lbs bags of concrete for the whole base. I found a place a few miles away from my home with a "You-Haul-It" concrete cart service I just hooked up to my light truck and drove home. Between the 2 of us and 1 laborer, it took under 3 hours. I was too nervous to float it or edge it thinking I would ruin it so its just a flat, level, screeded pad.
Also, I put vertical rebar in the 4 corners and then inserted (after screading) a few more vertical pieces so MOST concrete blocks have steel in them that is already attached to the footing. The rest will be filled with concrete later and steel just placed in there but eventually all tied together. Electrical conduit is put in for hooking up the future lights.
We feel like proud parents watching our concrete cure while our muscles spasm with joy (or soreness) at our progress. What a way start off the new year!
Question, how long should I wait until I start dry-stacking my blocks? It may take me a few days to pick them all up but I don't want to move too quickly. Plus the muscles really do need the rest.
Thanks to everyone, Dino
P.S.: I'm trying to get the Picasa web album linked up, so this will be my test to see if it works.
I have dug footings, installed rebar and poured my foundation for oven base.
Here are some stats on what I've done and why:
4 1/2 concrete blocks wide by 5 blocks deep. (those are 8x8x16 CMU concrete blocks. That's a pad I framed out at 82"x76"
It has 12" wide footings and 16" depth with the center pad area at 4"-5" deep with 1/2" rebar at the bottom (2), top and approx 12" squares across the top. All was placed on 2" dobee blocks to lift it off the ground.
It came to 1 1/2 yards plus 2 60lbs bags of concrete for the whole base. I found a place a few miles away from my home with a "You-Haul-It" concrete cart service I just hooked up to my light truck and drove home. Between the 2 of us and 1 laborer, it took under 3 hours. I was too nervous to float it or edge it thinking I would ruin it so its just a flat, level, screeded pad.
Also, I put vertical rebar in the 4 corners and then inserted (after screading) a few more vertical pieces so MOST concrete blocks have steel in them that is already attached to the footing. The rest will be filled with concrete later and steel just placed in there but eventually all tied together. Electrical conduit is put in for hooking up the future lights.
We feel like proud parents watching our concrete cure while our muscles spasm with joy (or soreness) at our progress. What a way start off the new year!
Question, how long should I wait until I start dry-stacking my blocks? It may take me a few days to pick them all up but I don't want to move too quickly. Plus the muscles really do need the rest.
Thanks to everyone, Dino
P.S.: I'm trying to get the Picasa web album linked up, so this will be my test to see if it works.
Comment