Re: A New Journey
1 3/4" would be a lot of mortar, especially as you have minimal mortar in your joins inside the rest of the dome. I think I would put some cut brick filler in there.
Or you could knock the 3 bricks over the arch out and do them again.
But you're right - nobody will ever see it. You could just leave it as is and correct a little bit in each of the remaining courses or finish with a teardrop shaped plug. You wouldn't be the first.