Outer Arch progress
Timber was delivered on the 14th, so that week became prioritised for building and putting up the timber framework for the terrace that will be over the oven. Roof sheets will be delivered mid Sept, so wanted to finish that and get back to the oven to do as much as possible before the roof sheets come. Ideally would like the chimney done so I am ready to cut the hole in the roof to install the double walled flue. That took me from 14-17 August.
Then back to the oven, and I decided to complete the front arch before starting on the dome bricks above the soldiers. Like the inner arch, I found the inner arch pretty straight forward and surprisingly easy to lay the bricks. I can only hope I find the dome bricks are as easy to lay.
I put a piece of 10mm ply in-between the rear and front arch to maintain a consistent gap in which I can insert the ceramic fibre covered with homebrew 5/1 vermicrete. It worked perfectly. I’m also happy the vent is exactly the size I planned on in sketchup, so my homemade vent cast will fit perfectly on top.
I knocked up an adjustable jig for the wet cutting saw so I can cut the top and bottom angles on the dome bricks. My first four courses above the soldiers are crucial to setting the curve of the Neapolitan dome. I tested my homemade jig for cutting the left and right sides of the dome course bricks, and it works perfectly. Photos to come.
I am planning on fitting the steel angle braces that will secure the stainless steel straps around the soldier course. I will update more info on this soon.
I tested positive for COVID this week, and it knocked me for six. Been layed up since Wednesday unable to do anything on the oven, but back on the computer today planning. Hope to be back on the dome tomorrow, will see how my energy levels go.
Timber was delivered on the 14th, so that week became prioritised for building and putting up the timber framework for the terrace that will be over the oven. Roof sheets will be delivered mid Sept, so wanted to finish that and get back to the oven to do as much as possible before the roof sheets come. Ideally would like the chimney done so I am ready to cut the hole in the roof to install the double walled flue. That took me from 14-17 August.
Then back to the oven, and I decided to complete the front arch before starting on the dome bricks above the soldiers. Like the inner arch, I found the inner arch pretty straight forward and surprisingly easy to lay the bricks. I can only hope I find the dome bricks are as easy to lay.
I put a piece of 10mm ply in-between the rear and front arch to maintain a consistent gap in which I can insert the ceramic fibre covered with homebrew 5/1 vermicrete. It worked perfectly. I’m also happy the vent is exactly the size I planned on in sketchup, so my homemade vent cast will fit perfectly on top.
I knocked up an adjustable jig for the wet cutting saw so I can cut the top and bottom angles on the dome bricks. My first four courses above the soldiers are crucial to setting the curve of the Neapolitan dome. I tested my homemade jig for cutting the left and right sides of the dome course bricks, and it works perfectly. Photos to come.
I am planning on fitting the steel angle braces that will secure the stainless steel straps around the soldier course. I will update more info on this soon.
I tested positive for COVID this week, and it knocked me for six. Been layed up since Wednesday unable to do anything on the oven, but back on the computer today planning. Hope to be back on the dome tomorrow, will see how my energy levels go.